|
Location: |
Danabari and Chisapani VDC, Ilam District, Eastern Development Region of Nepal |
|
Purpose of Project: |
To supply hydro-electricity for domestic use by connecting to Integrated Nepal Power System (INPS) |
|
Hydrology: |
|
|
Catchment Area |
589.0 km2 |
|
Average Flow |
32.66 m3/s (minimum monthly flow 7.22 m3/s) |
|
Design Flow |
23.43 m3/s (40% exceedence flow) |
|
90% Exceedence flow |
7.48 m3/s |
|
Design Flood (Q100) |
2070 m3/s |
|
1000 years Flood (Q1000) |
3007 m3/s |
|
Diversion Dam: |
|
|
Type |
Concrete gravity dam |
|
Shape |
Ogee-profile |
|
Crest Elevation |
321.1 m above msl |
|
Crest Length |
91.12 m |
|
Height |
5.1 m (from original river bed level) |
|
Designed flood (Q100) level |
325.6 m above msl |
|
River Diversion During Construction: |
|
Alignment |
Along the river channel |
|
Diversion flow |
250 m3/s |
|
Coffer dams |
Two cofferdams facilitating stage1 and stage 2 concreting (Total coffer dam length = 377.5 m) |
|
Intake spillway/ Undersluice: |
|
|
Type |
Over-flow weir with under-sluice (3@2x4m width) |
|
Crest Elevation |
321.1 m above msl (undersluice 314.5 m above msl) |
|
Length |
111.12 mm |
|
Design Flood (Q100) |
2070 m3/s |
|
Intake: |
|
|
Type |
Frontal Intake, submerged, over the undersluice |
|
Number of Orifices |
3 |
|
Bottom Elevation of Orifice |
317.0 m amsl |
|
Top Elevation of Orifice |
320.0 m above msl |
|
Length of Orifices |
20.0 m (with inner piers, clear opening of each orifice = 2.55 x 6 m width) |
|
Intake canal: |
|
|
Type |
RCC open canal |
|
Maximum height |
3.0 m |
|
Average Width |
6.8 m |
|
Approach Culvert: |
|
|
Type |
RCC pressurized conduit |
|
Number |
2 |
|
Average Height |
3.0 m (internal) |
|
Average Width |
3.0 m (internal) |
|
Total Length of outer branch Total length of inner branch Invert Level |
62.69 m 40.98 m 317.10 m |
|
Settling Basin: |
|
|
Type |
Conventional flushing |
|
Number of Chamber |
4 (four) |
|
Top elevation |
322.4 m above msl |
|
Normal Operation elevation |
320.50 m above msl |
|
Length of the basin |
75 m (settling zone) |
|
Average Height |
5.85 m |
|
Bottom width per Chamber |
9.5 m c/c |
|
Headrace Culvert: |
|
|
Type |
RCC pressurized culvert |
|
Length |
1055.69 m |
|
Height |
3.3 m |
|
Bottom width |
3.5 m |
|
Longitudinal slope |
1:1500 (V:H) |
|
Headrace Tunnel: |
|
|
Length |
2198.0 m (incl. 66 m after surge-tank) |
|
Dimensions |
Inverted D 3.8 x3.96 m, (13.1 m2-finish) |
|
Discharge |
23.43 m3/s |
|
Surge Shaft dimensions: |
|
|
Type |
Vertical, circular section |
|
Height |
35.0 m |
|
Diameter |
8.0 m (finish) |
|
Penstock |
|
|
Length |
316.38 m (273.6 m up to bifurcation) |
|
Diameter/thickness |
2.6 m to 1.5 m internal diameter/10 mm to 25 mm thickness |
|
Power Facilities: |
|
|
Powerhouse Type |
Semi-surface |
|
Dimensions |
36 m x 22 m |
|
Gross Head |
122.1 m (321.1 – 199.0 m above msl) |
|
Net Head |
108.93 m |
|
Installed capacity |
22.0 MW (3x7.33 MW) |
|
Dry energy |
22.11 GWh |
|
Wet energy |
103.03 GWh |
|
Annual Net Energy Output |
125.14 GWh |
|
Tailrace Culvert: |
|
|
Type |
RCC canal |
|
Length |
229.5 m |
|
Height |
3.3 m |
|
Width |
3.5 m |
|
Longitudinal slope |
1:450 (V:H) |
|
Power Transformer |
|
|
Type |
3-phase, two windings, oil immersed transformer with off load tap-changer; |
|
Installation |
Outdoor; |
|
Rated power |
10,000 kVA and 20,000 kVA; |
|
Transmission Facilities: |
|
|
Transmission line length |
11.6 km |
|
Voltage level |
132 kV, single circuit |
|
|
|
|
Project Cost at completion |
3,295 million NPR |